Are Our Projects Moving?

Every project begins with a plan. Communities spend time and money creating engineering reports, master plans, feasibility studies, and capital improvement plans. Those documents should become roadmaps, not shelves of forgotten reports. This page follows major public projects from adoption to implementation using the City's own published timelines.

How to Read This Page

Each project follows the same format.

Planning & Development

When the project was being researched, developed, or considered before formal adoption.

When the project or plan became official.

Plan Adopted
Published Timeline

What the City said would happen next.

Current Status

Based only on publicly available documents.

Accountability Questions

Questions that naturally arise from comparing the adopted timeline with current public information.

Project Status Key

🟢 Completed

Project milestone has been completed or officially adopted.

🟡 In Progress

Work has begun or is actively underway based on publicly available information.

⚪ No Public Progress

No public evidence has been identified that work has started or advanced.

Project status is based on publicly available documents, commission meetings, staff reports, published updates, and official records. Statuses are updated as new information becomes available.

Project One: Downtown Master Plan

Status: 🟡 Early Implementation

Plan Adopted: September 3, 2024.

The Promise

The Downtown Master Plan states that it will prioritize future public improvements and investments, provide a framework for implementation, and guide Downtown development over the next 10 to 15 years.

Published Timeline

🟢

2024 – 🟢 Plan adopted; 🟢 Community engagement completed; 🟢 Housing Study completed; 🟢 Parking Study completed

🟡

Years 1–2 (2025–2026) – The Implementation Action Plan identifies a number of early implementation items, including parking management, regulatory tools, streetscape improvements, and wayfinding initiatives.

Early Implementation Table

Early Implementation Item

Parking Management

Regulatory Tools

Wayfinding & Gateways

Streetscape Improvements

Planned Phase

Years 1–2

Years 1–2

Years 1–2

Years 1–2

Current Public Status

🟡

Accountability Clock

Plan Adopted: September 2024

Current Year: 2026

Implementation Window: Years 1–2

Accountability Questions 

  • Which Year 1 priorities have been completed?
  • Has the City published an annual implementation report?
  • Has the implementation schedule changed?
  • Which projects remain on schedule?
Did You Know?

The Downtown Master Plan identifies parking management as an important part of improving downtown access. One option that has been proposed is replacing the current two-hour parking restriction with modern self-pay parking kiosks.

 

Under this approach, visitors could continue parking for free for a short visit, while those who need additional time could simply pay to remain in their space. Rather than moving vehicles every two hours, the system would generate revenue that could help pay for the equipment, support downtown improvements, and potentially reduce or reassign staff time currently devoted to parking enforcement.

 

Modern solar-powered pay stations typically cost $6,000 to $10,000 each, avoid expensive electrical installation, and can manage dozens of parking spaces from a single kiosk.

 

If it aligns with the Downtown Master Plan and has the potential to improve convenience while generating additional revenue, why hasn't it been explored further or presented to the City Commission as a policy option for public discussion?

The Bottom Line

The City has completed the planning phase. The next step is helping residents understand which implementation priorities have begun and how progress is being reported.

Railroad Crossing

🟡 Planning Phase

Stormwater Utility

🟡 Planning Complete

Downtown Master Plan

🟡 Early Implementation

Parks Master Plan

🟡 Implementation Beginning

How to Read This Page

Each project follows the same format. This standardized reporting structure ensures direct comparison between published promises and documented reality.

Plan Adopted

When the project or plan became official.

Published Timeline

What the City said would happen next.

Current Status

Based only on publicly available documents.

Accountability Questions

Questions arising from comparing adopted timelines with reality.

Project Two: Stormwater Utility

Status: 🟡 Planning Complete

Plan Adopted: Stormwater Utility Feasibility Study, September 2024.

The Promise

The feasibility study concludes that Livingston's stormwater system faces aging infrastructure, deferred maintenance, flooding challenges, and lacks a dedicated funding source. It evaluates whether creating a Stormwater Utility is the right long-term solution and recommends options for funding, staffing, reserves, and capital improvements.

Completed Planning
Published Timeline & Progress

Asset inventory

Population projections

Feasibility Study

🟢

Capital Improvement Plan

🟢

Revenue Plan

🟢

Utility Structure

🟡

Capital Projects

🟡

Long-Term Reporting

Revenue analysis

Utility rate options

Equipment plan

Five-Year Capital Improvement Plan

Reserve recommendations

Operating budget

Utility implementation options

Future Milestones
2025

Initial capital projects

2026–2029

Five-Year Capital Improvement Program

Beyond

Additional long-term capital projects

Accountability Questions
Bottom Line

The planning work is largely complete. The focus now shifts from planning to implementation.

  • Which recommendations have been adopted?
  • Which capital projects have started?
  • Has the utility structure been finalized?
  • Is the City reporting annual progress?

Project Three: Railroad Crossing

Status: 🟡 Planning

The Stormwater Utility Feasibility Study identifies a Railroad Crossing project within its Capital Improvement Plan and Five-Year Capital Improvement Program. The February 3, 2026 commission discussion also addressed funding available for alternatives analysis.

What does "Railroad Crossing" mean?
The term railroad crossing can mean different things to different people. Some residents understand it to mean a new roadway connecting the north and south sides of Livingston, while others use it to describe infrastructure improvements associated with the City's stormwater planning. Understanding how the term has been used in official documents is important when evaluating the project's progress. Read our blog for a deeper look at the history, documents, and public discussions surrounding this project.
Published Timeline
2023

Stormwater Preliminary Engineering Report – Railroad Crossing identified – 🟢

2024

Stormwater Utility Feasibility Study – Railroad Crossing remains in Capital Improvement Plan – 🟢

2026

Alternatives analysis discussed – 🟡

Future

Construction – ⚪

Project Scorecard

Planning

🟢

Engineering Studies

🟢

Funding Discussion

🟢

Final Design

Construction Funding

Construction

Accountability Questions
  • Has a preferred alternative been selected?
  • Has final engineering begun?
  • Has construction funding been secured?
  • What is the next public milestone?
The Bottom Line

Planning has occurred over multiple years. The next publicly visible milestones are final design, funding, and construction.

Project Four: Parks System Master Plan

Status: 🟡 Implementation Beginning
Plan Adopted: November 2025

The Promise

The Parks System Master Plan establishes a 10–15 year roadmap for improving Livingston's parks through prioritized investments, facility upgrades, trail connectivity, and implementation planning.

✔ TOP PRIORITY

Walking and hiking trails

✔ TOP PRIORITY

Paved bike trails

✔ TOP PRIORITY

Indoor walking running track

* Residents also identified connectivity, maintenance, and additional indoor recreation as major priorities.

Completed Planning

Plan readiness checklist based on November 2025 deliverables.

✔ Community survey

✔ Facility assessment

✔ Level of Service analysis

✔ Gap analysis

✔ Action Plan

✔ Cost estimates

✔ Individual park concepts

Accountability Clock
Plan Adopted: November 2025
Current Year: 2026
Current Phase: Beginning Implementation

Accountability Questions

Bottom Line

The Parks Master Plan provides a detailed roadmap. Future updates should allow residents to follow implementation over time.

• Which park projects have received funding?

• Which trail improvements have begun?

• Which recommendations are scheduled first?

• Will annual implementation updates be published?

Questions We're Following

Has the City published implementation updates?

Which recommendations have been completed?

Where can residents track progress?

Are projects following the published timelines?

What is the next milestone for each project?

Source Documents

Stormwater Utility Feasibility Study – September 2024

Downtown Master Plan – September 2024

Parks System Master Plan – November 2025

Stormwater Preliminary Engineering Report

February 3, 2026 Commission Meeting

Methodology

This page compares adopted plans with publicly available implementation information. Projects are evaluated using the City's own documents. No project is labeled complete unless supported by public records. No project is labeled behind schedule unless the adopted documents establish a timeline that has passed without documented completion. Questions are presented where additional public reporting would help residents understand implementation.